Home / Guides / California laborer prevailing wage: groups, titles and rates
Guide · Laborers
California laborer prevailing wage by group
A California laborer's prevailing wage depends on two things: where the job is and which group the work falls in. Under DIR's 2026-2 determinations, Group 1 pays $71.96 an hour in total across 40 Northern California counties, $72.96 in 6 Bay Area counties, $78.65 in Southern California and $76.87 for San Diego building work.
From DIR's laborer determinations NC-23-102-1-2026-2 (Northern California), SC-23-102-2-2026-1 (Southern California) and the two San Diego files, 2026-2 release. Rates are total straight-time hourly rates, base plus employer payments. Checked against dir.ca.gov on October 24, 2026. Published October 25, 2026.
Find the group for a job
The same work sits in a different group, at a different rate, on each side of the state. Northern California figures are Area 1; Area 2 is $1.00 less.
| Job | Northern California title | NC group, rate | Southern California title | SC group, rate |
|---|---|---|---|---|
| Flagger | Flagperson/pedestrian monitor | Group 3 · $72.71 | Flagman | Group 1 · $78.65 |
| Cleanup | All final cleanup of debris, grounds and buildings near the completion of the project | Group 4 · $66.40 | Laborer, General Cleanup | Group 1 · $78.65 |
| Compactor / tamper | Compactors of all types | Group 1 · $72.96 | Compactor (all types including Tampers, Barko, Wacker) | Group 3 · $79.75 |
| Concrete saw | Concrete sanders, concrete saw | Group 1 · $72.96 | Concrete Saw Man, Cutting Walls or Flat Work, Scoring old or new concrete | Group 4 · $81.30 |
| Pipelayer | Pipelayers (including grade checking in connection with pipelaying) | Group 1 · $72.96 | Pipelayer | Group 4 · $81.30 |
| Hazardous waste | Certified hazardous waste worker (including lead abatement) | Group 1 · $72.96 | Toxic Waste Removal | Group 5 · $81.65 |
| Blaster | Blasters and powderman | Group 1 (A) · $73.18 | Blasters Powderman | Group 5 · $81.65 |
Titles as DIR prints them in each determination's group lists (Northern California pages 5 to 7, Southern California page 2). Northern rates from Alameda County, southern from Los Angeles County.
Group numbers run in opposite directions
Total hourly rate for Groups 1 to 5, Northern California Area 1 against Southern California. Northern California has no Group 5.
In the Southern California determination the groups climb: Group 1 is the lowest at $78.65 and Group 5 the highest at $81.65, $3.00 apart. Flaggers, fire watchers and general cleanup laborers are in Group 1; blasters, welders and toxic waste removal are in Group 5.
In Northern California, Groups 1 to 3 sit within 25 cents of each other ($72.71 to $72.96 in Area 1), and Group 4 drops to $66.40. Group 4 is the final cleanup group: "all final cleanup of debris, grounds and buildings near the completion of the project," new-construction window washing, and brick and material cleaners on the job site. The higher-paid specialties sit in lettered subgroups instead. Group 1 (A) covers blasting and powder work, Group 1 (C) burning and welding, Group 1 (E) bell-hole footings and shafts, and Group 6 structural nozzlemen, the highest-paid group at $73.92.
A payroll admin who moves a crew from Sacramento to Riverside can't carry the group number across. A Group 1 flagger in the south would be Group 3 in the north, and a northern Group 1 pipelayer is Group 4 in the south.
What each Northern California group covers
A few titles from each list in NC-23-102-1-2026-2. Group 1 alone has 49 titles; every county laborer page lists them all.
| Group | Area 1 | Area 2 | Example titles |
|---|---|---|---|
| Group 1 | $72.96 | $71.96 | Caulkers, banders, pipewrappers, conduit layers, plastic pipe layers; Certified asbestos and mold removal worker; Compactors of all types; Concrete and magnesite mixer and ½ yard |
| Group 2 | $72.81 | $71.81 | Asphalt shovelers; Concrete laborers |
| Group 3 | $72.71 | $71.71 | Construction laborers including bridge laborers, general laborers and cleanup laborers; Demolition worker; Dumpman, load spotter |
| Group 4 | $66.40 | $65.40 | All final cleanup of debris, grounds and buildings near the completion of the project including but not limited to street cleaners; Brick cleaners |
| Group 6 | $73.92 | $72.92 | Structural nozzleman |
| Group 7 | $60.59 | $59.89 | Entry level landscape laborer |
Group 7 is entry-level landscape work, paid in three six-month stages: $60.59, $64.63, $68.67 in Area 1. Group 1 (B), sewer cleaners, is paid at Group 1 rates plus a daily premium: $4.00 a day for work with raw sewage in small-diameter sewers and $5.00 a day inside recently active large-diameter sewers and manholes.
Two footnotes change the hourly figure. Footnote b adds zone pay of $3.00 an hour, factored at the overtime multiple, "for work performed outside the free zone described by the boundaries along township and range lines"; the free-zone map is in the determination's travel and subsistence provision. Group 1 (D) trackmen get $0.25 an hour above their regular rate (footnote a). Special single and second shifts have their own table in the same PDF, determination NC-23-102-1-2026-2A, where Group 1 in Area 1 is $75.96.
Area 1 and Area 2
The Northern California laborer determination has two areas. Area 1 is Santa Clara, Alameda, Contra Costa, San Francisco, San Mateo and Marin. Area 2 is the other 40 counties it covers, including Sacramento, Fresno, San Joaquin and 37 more. The areas differ by $1.00 of base wage in every group; employer payments are the same $32.31 in both ($12.00 health and welfare, $15.46 pension, $4.00 vacation and holiday, $0.52 training, $0.33 other).
This map is the laborers' own. Napa, Solano and Sonoma are Bay Area 1 counties for carpenters but Area 2 for laborers, so check the area inside the file for the trade you are paying. The carpenter guide shows the carpenter areas.
San Diego splits by type of work. Building construction (SD-23-102-4) pays $76.87 for Group 1; engineering construction (SD-23-102-3) pays $78.65, the same as Southern California. Both 2026-2 San Diego files say they apply to projects advertised for bids on or after October 9, 2026; DIR reissued both on September 29, 2026.
Overtime for laborers
| Group 1 | Straight | Daily/Saturday OT | Sunday/holiday |
|---|---|---|---|
| Northern California, Area 1 | $72.96 | $93.29 | $113.61 |
| Northern California, Area 2 | $71.96 | $91.79 | $111.61 |
| Southern California | $78.65 | $103.25 | $127.85 |
Laborer determinations print one overtime rate for weekdays and Saturdays and a second for Sundays and holidays. In Northern California, footnote d says the daily/Saturday rate "applies to the first 4 daily overtime hours worked on Monday through Friday and the first 12 hours worked on Saturday; all other time is paid at the Sunday and holiday overtime hourly rate." Southern California's footnote c switches to double time for "any hours worked over 12 hours in a single workday." Its footnote d allows a Saturday at straight time when the job "is shut down during work week due to inclement weather or similar Act of God, or a situation beyond the employer's control."
The overtime figures follow the same rule as other crafts: the multiplier applies to the base wage and the employer payments are added on top, so Northern California's $93.29 is 1.5 × $40.65 plus $32.31.
When a task isn't on any list
The group lists are long but not complete, and some titles carry conditions in parentheses that decide the group, such as Southern California's "Driller, Jackhammer, 2 1/2 ft. drill steel or longer" in Group 3. DIR publishes an advisory scope of work for each determination, linked from the determinations menu beside the holiday and travel documents, which describes the work the craft covers. When the scope still leaves the answer open, DIR's Research Unit takes questions at (415) 703-4774, the number printed on the laborer determinations.
A laborer who flags traffic in the morning and runs a compactor in the afternoon in Southern California moves from Group 1 to Group 3, $1.10 an hour apart; in Northern California the same two tasks are Group 3 and Group 1, $0.25 apart.
Laborer Group 1 since 2024
Group 1 total hourly rate in each DIR period, from the laborer determination DIR published for that period.
| Group 1 | 2024-2 | 2025-1 | 2025-2 | 2026-1 | 2026-2 | Change |
|---|---|---|---|---|---|---|
| Northern California, Area 1 | $67.66 | $67.66 | $70.31 | $70.31 | $72.96 | +$5.30 |
| Northern California, Area 2 | $66.66 | $66.66 | $69.31 | $69.31 | $71.96 | +$5.30 |
| Southern California | $71.69 | $71.69 | $75.09 | $75.09 | $78.65 | +$6.96 |
| San Diego, building | $69.68 | $69.68 | $73.31 | $73.31 | $76.87 | +$7.19 |
Southern California laborers have out-earned Northern California's Area 1 in every period since 2024-2, and the gap widened from $4.03 to $5.69. Over the two years Southern California rose $6.96 and Northern California $5.30. The figures in each table cell link to the DIR file they came from.
Raises already set
All three laborer determinations carry a double asterisk, so their next increases are fixed and must be paid on work after each date (FAQ Q8).
| Determination | Increases to the total | Sum |
|---|---|---|
| Northern California | June 28, 2027 +$3.62 · June 26, 2028 +$3.61 · June 25, 2029 +$3.51 · July 1, 2030 +$3.51 | +$14.25 |
| Southern California | July 1, 2027 +$3.66 · July 1, 2028 +$3.76 · July 1, 2029 +$4.01 | +$11.43 |
| San Diego, building | July 1, 2027 +$3.66 · July 1, 2028 +$4.65 · July 1, 2029 +$4.90 | +$13.21 |
DIR's increase files say how each raise may be split. The Northern California file, NC-023-102-1-Pre, allocates the June 28, 2027 increase as "$3.60 to wages and/or employer payments and $0.02 to Other," which fixes the increase to the total and leaves open how much of it goes to the base wage.
Related
- Laborer rates in all 58 counties, with every group on each county page.
- Laborer-family trades with their own determinations: tunnel workers, landscape and irrigation laborers, asbestos and lead abatement laborers.
- Apprentice rates: Area 1 laborer apprentices are paid a percentage of the Group 3 journeyman rate.
- DIR, NC-23-102-1-2026-2, SC-23-102-2-2026-1, SD-23-102-4, and earlier periods linked in the history table. DIR FAQ.