Home / Oklahoma / Osage County / Operating Engineer
Osage County, OK · Operating Engineer
Operating Engineer prevailing wage in Osage County, Oklahoma
$57.14an hour, base wage + fringe benefits (our sum)
$38.09 base wage + $19.05 fringe benefits
POWER EQUIPMENT OPERATOR: GROUP 1 ALL CRANE TYPE EQUIPMENT 200 TON AND LARGER AND INCLUDING 400 TON CAPACITY CRANES. ALL TOWER CRANES · ENGI0627-020
$27.02an hour, base wage + fringe benefits (our sum)
$17.02 base wage + $10.00 fringe benefits
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE · SUOK2017-008
$15.16an hour, base wage + fringe benefits (our sum)
$15.16 base wage + $0.00 fringe benefits
POWER EQUIPMENT OPERATOR: BACKHOE/TRACKHOE (REMAINING COUNTIES) · SUOK2011-004
$57.14an hour, base wage + fringe benefits (our sum)
$38.09 base wage + $19.05 fringe benefits
POWER EQUIPMENT OPERATOR: GROUP 1 ALL CRANE TYPE EQUIPMENT 200 TON AND LARGER AND INCLUDING 400 TON CAPACITY CRANES. ALL TOWER CRANES · ENGI0627-014
On federally funded or assisted building construction in Osage County, an operating engineer must be paid at least $57.14 an hour: a $38.09 base wage plus $19.05 in fringe benefits, under wage determination OK20260050 (modification 1). DOL prints no total, so $57.14 is our sum of the two.
Wage determination OK20260050, modification 1, published May 18, 2026, for building construction; rate identifier ENGI0627-020 (June 1, 2025). Checked against sam.gov on October 25, 2026.
On federally funded or assisted residential construction in Osage County, an operating engineer must be paid at least $27.02 an hour: a $17.02 base wage plus $10.00 in fringe benefits, under wage determination OK20260080 (modification 1). DOL prints no total, so $27.02 is our sum of the two.
Wage determination OK20260080, modification 1, published May 18, 2026, for residential construction; rate identifier SUOK2017-008 (April 3, 2019). Checked against sam.gov on October 25, 2026.
On federally funded or assisted highway construction in Osage County, an operating engineer must be paid at least $15.16 an hour: a $15.16 base wage plus $0.00 in fringe benefits, under wage determination OK20260017 (modification 1). DOL prints no total, so $15.16 is our sum of the two.
Wage determination OK20260017, modification 1, published May 18, 2026, for highway construction; rate identifier SUOK2011-004 (April 18, 2011). Checked against sam.gov on October 25, 2026.
On federally funded or assisted heavy construction in Osage County, an operating engineer must be paid at least $57.14 an hour: a $38.09 base wage plus $19.05 in fringe benefits, under wage determination OK20260030 (modification 1). DOL prints no total, so $57.14 is our sum of the two.
Wage determination OK20260030, modification 1, published May 18, 2026, for heavy construction; rate identifier ENGI0627-014 (June 1, 2025). Checked against sam.gov on October 25, 2026.
Davis-Bacon is the only prevailing wage here (federally funded or assisted work). Oklahoma's law was invalidated in 1995 and its public-works wage rules are revoked (DOL state table).
DOL lists 45 operating engineer rates for Osage County, from $11.71 to $57.14 an hour. See all of them.
Base wage and fringe benefits: $38.09 + $19.05
The base wage is the taxable hourly wage. DOL prints the fringe benefits as one hourly figure, not itemized; it can go to health, pension, vacation and training plans, or be paid as cash where the state allows.
| Base wage (taxable) | $38.09 |
| Fringe benefits (one figure, not itemized) | $19.05 |
| Base + fringe benefits (our sum; DOL prints no total) | $57.14 |
Base wage and fringe benefits: $17.02 + $10.00
The base wage is the taxable hourly wage. DOL prints the fringe benefits as one hourly figure, not itemized; it can go to health, pension, vacation and training plans, or be paid as cash where the state allows.
| Base wage (taxable) | $17.02 |
| Fringe benefits (one figure, not itemized) | $10.00 |
| Base + fringe benefits (our sum; DOL prints no total) | $27.02 |
Base wage and fringe benefits: $15.16 + $0.00
The base wage is the taxable hourly wage. DOL prints the fringe benefits as one hourly figure, not itemized; it can go to health, pension, vacation and training plans, or be paid as cash where the state allows.
| Base wage (taxable) | $15.16 |
| Base + fringe benefits (our sum; DOL prints no total) | $15.16 |
Base wage and fringe benefits: $38.09 + $19.05
The base wage is the taxable hourly wage. DOL prints the fringe benefits as one hourly figure, not itemized; it can go to health, pension, vacation and training plans, or be paid as cash where the state allows.
| Base wage (taxable) | $38.09 |
| Fringe benefits (one figure, not itemized) | $19.05 |
| Base + fringe benefits (our sum; DOL prints no total) | $57.14 |
When does this rate change?
- A contract keeps the wage determination in its bid documents. Modifications published before bid opening apply to it, though one published less than 10 days before can be left out if the agency finds there isn't time to tell bidders (29 CFR 1.6(c)).
- DOL changes a WD by publishing a numbered modification on SAM.gov. This page reads the modification named in the Source line; the Oklahoma change log lists what each one changed.
Every operating engineer rate in Osage County
As DOL lists them. The highlighted row is the one this page leads with.
| Classification | Base wage | Fringe benefits | Total rate | WD |
|---|---|---|---|---|
| POWER EQUIPMENT OPERATOR: GROUP 8 FORKLIFTBuildingENGI0627-020 | $28.77 | $19.05 | $47.82 | OK20260050 Mod 1 |
| POWER EQUIPMENT OPERATOR: GROUP 4 CRANES WITH BOOM INCL. JIB LESS THAN 100 FT AND LESS THAN 3 CU. YD.; OVERHEAD MONORAIL CRANE AND BULLDOZERBuildingENGI0627-020 | $34.07 | $19.05 | $53.12 | OK20260050 Mod 1 |
| POWER EQUIPMENT OPERATOR: GROUP 3 ALL CRANE TYPE EQUIPMENT 50 TON CAPACITY AND LARGER CRANES, AND LESS THAN 100 TON CAPACITY. CRANE EQUIPMENT (AS RATED BY MFG.) 3 CU. YD. AND OVER GUY DERRICK WHIRLEY POWER DRIVEN HOLE DIGGER (WITH 30' AND LONGER MAST)BuildingENGI0627-020 | $35.40 | $19.05 | $54.45 | OK20260050 Mod 1 |
| POWER EQUIPMENT OPERATOR: GROUP 2 ALL CRANE TYPE EQUIPMENT 100 TON CAPACITY AND LARGER CRANES, AND LESS THAN 200 TON CAPACITYBuildingENGI0627-020 | $36.14 | $19.05 | $55.19 | OK20260050 Mod 1 |
| POWER EQUIPMENT OPERATOR: GROUP 1 ALL CRANE TYPE EQUIPMENT 200 TON AND LARGER AND INCLUDING 400 TON CAPACITY CRANES. ALL TOWER CRANESBuildingENGI0627-020 | $38.09 | $19.05 | $57.14 | OK20260050 Mod 1 |
| OPERATOR: LOADER (FRONT END)BuildingSUOK2012-030 | $16.18 | $0.00 | $16.18 | OK20260050 Mod 1 |
| OPERATOR: GRADER/BLADEBuildingSUOK2012-030 | $14.28 | $1.70 | $15.98 | OK20260050 Mod 1 |
| OPERATOR: BULLDOZERBuildingSUOK2012-030 | $20.64 | $2.35 | $22.99 | OK20260050 Mod 1 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOEBuildingSUOK2012-030 | $17.23 | $4.08 | $21.31 | OK20260050 Mod 1 |
| OPERATOR: ASPHALT PAVERBuildingSUOK2012-030 | $16.88 | $0.00 | $16.88 | OK20260050 Mod 1 |
| POWER EQUIPMENT OPERATOR: BACKHOE/TRACKHOE (REMAINING COUNTIES)HighwaySUOK2011-004 | $15.16 | $0.00 | $15.16 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (TRENCHER)HighwaySUOK2011-004 | $13.87 | $0.00 | $13.87 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (TRACTOR/BOX BLADE)HighwaySUOK2011-004 | $13.67 | $0.00 | $13.67 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (SCRAPER)HighwaySUOK2011-004 | $13.34 | $0.00 | $13.34 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (ROLLER (DIRT COMPACTION))HighwaySUOK2011-004 | $11.71 | $0.00 | $11.71 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (ROLLER (ASPHALT))HighwaySUOK2011-004 | $12.79 | $0.00 | $12.79 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (OILER)HighwaySUOK2011-004 | $15.28 | $0.00 | $15.28 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (MIXER)HighwaySUOK2011-004 | $14.43 | $0.00 | $14.43 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (MILLING MACHINE)HighwaySUOK2011-004 | $14.56 | $0.00 | $14.56 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (MECHANIC)HighwaySUOK2011-004 | $17.46 | $0.00 | $17.46 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (LOADER (FRONT END))HighwaySUOK2011-004 | $13.81 | $0.00 | $13.81 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (GRADER/BLADE)HighwaySUOK2011-004 | $16.68 | $0.00 | $16.68 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (EXCAVATOR)HighwaySUOK2011-004 | $14.99 | $0.00 | $14.99 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (CRANE)HighwaySUOK2011-004 | $17.45 | $0.00 | $17.45 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (CONCRETE PAVING MACHINE)HighwaySUOK2011-004 | $14.11 | $0.00 | $14.11 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (BULLDOZER)HighwaySUOK2011-004 | $14.28 | $0.00 | $14.28 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (BROOM)HighwaySUOK2011-004 | $11.97 | $0.00 | $11.97 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (BOBCAT/SKID LOADER)HighwaySUOK2011-004 | $12.24 | $0.00 | $12.24 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (ASPHALT PAVING MACHINE)HighwaySUOK2011-004 | $13.95 | $2.75 | $16.70 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: (ASPHALT PAVER SCREED)HighwaySUOK2011-004 | $12.96 | $0.00 | $12.96 | OK20260017 Mod 1 |
| POWER EQUIPMENT OPERATOR: GROUP 6 ROLLER (ASPHALT AND DIRT)HeavyENGI0627-014 | $30.87 | $19.05 | $49.92 | OK20260030 Mod 1 |
| POWER EQUIPMENT OPERATOR: GROUP 4 CRANES WITH BOOM INCL. JIB LESS THAN 100 FT AND LESS THAN 3 CU. YD.; OVERHEAD MONORAIL CRANEHeavyENGI0627-014 | $34.07 | $19.05 | $53.12 | OK20260030 Mod 1 |
| POWER EQUIPMENT OPERATOR: GROUP 3 ALL CRANE TYPE EQUIPMENT 50 TON CAPACITY AND LARGER CRANES, AND LESS THAN 100 TON CAPACITY. CRANE EQUIPMENT (AS RATED BY MFG.) 3 CU. YD. AND OVER GUY DERRICK WHIRLEY POWER DRIVEN HOLE DIGGER (WITH 30' AND LONGER MAST)HeavyENGI0627-014 | $35.40 | $19.05 | $54.45 | OK20260030 Mod 1 |
| POWER EQUIPMENT OPERATOR: GROUP 2 ALL CRANE TYPE EQUIPMENT 100 TON CAPACITY AND LARGER CRANES, AND LESS THAN 200 TON CAPACITYHeavyENGI0627-014 | $36.14 | $19.05 | $55.19 | OK20260030 Mod 1 |
| POWER EQUIPMENT OPERATOR: GROUP 10 OILERHeavyENGI0627-014 | $27.25 | $19.05 | $46.30 | OK20260030 Mod 1 |
| POWER EQUIPMENT OPERATOR: GROUP 1 ALL CRANE TYPE EQUIPMENT 200 TON AND LARGER AND INCLUDING 400 TON CAPACITY CRANES. ALL TOWER CRANESHeavyENGI0627-014 | $38.09 | $19.05 | $57.14 | OK20260030 Mod 1 |
| OPERATOR: TRACKHOEHeavySUOK2012-008 | $18.54 | $2.78 | $21.32 | OK20260030 Mod 1 |
| OPERATOR: SCRAPERHeavySUOK2012-008 | $16.00 | $1.55 | $17.55 | OK20260030 Mod 1 |
| OPERATOR: MECHANICHeavySUOK2012-008 | $19.61 | $9.39 | $29.00 | OK20260030 Mod 1 |
| OPERATOR: LOADER (FRONT END)HeavySUOK2012-008 | $14.01 | $0.00 | $14.01 | OK20260030 Mod 1 |
| OPERATOR: GRADER/BLADEHeavySUOK2012-008 | $17.76 | $3.87 | $21.63 | OK20260030 Mod 1 |
| OPERATOR: DRILLHeavySUOK2012-008 | $17.15 | $0.78 | $17.93 | OK20260030 Mod 1 |
| OPERATOR: BULLDOZERHeavySUOK2012-008 | $17.98 | $1.75 | $19.73 | OK20260030 Mod 1 |
| OPERATOR: BACKHOE/EXCAVATORHeavySUOK2012-008 | $16.62 | $3.10 | $19.72 | OK20260030 Mod 1 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOEResidentialSUOK2017-008 | $17.02 | $10.00 | $27.02 | OK20260080 Mod 1 |
How Osage County compares
The main operating engineer rate in every county that has one, and how the pay splits here and nearby. All bars use the same scale.
Every county in Oklahoma
Wage and fringe benefits, nearby
- Osage Countybase $38.09$57.14
- Pawnee Countybase $38.09$57.14
- Washington Countybase $38.09$57.14
- Tulsa Countybase $38.09$57.14
Operating Engineer rates in nearby counties
Current DOL rates. Davis-Bacon rates are set for groups of counties, so neighbours often share them; the county where the work is done decides.
| County | Classification | Base wage | Total rate | vs Osage County |
|---|---|---|---|---|
| Osage County | POWER EQUIPMENT OPERATOR: GROUP 1 ALL CRANE TYPE EQUIPMENT 200 TON AND LARGER AND INCLUDING 400 TON CAPACITY CRANES. ALL TOWER CRANES | $38.09 | $57.14 | |
| Pawnee County | POWER EQUIPMENT OPERATOR: GROUP 1 ALL CRANE TYPE EQUIPMENT 200 TON AND LARGER AND INCLUDING 400 TON CAPACITY CRANES. ALL TOWER CRANES | $38.09 | $57.14 | same |
| Washington County | POWER EQUIPMENT OPERATOR: GROUP 1 ALL CRANE TYPE EQUIPMENT 200 TON AND LARGER AND INCLUDING 400 TON CAPACITY CRANES. ALL TOWER CRANES | $38.09 | $57.14 | same |
| Tulsa County | POWER EQUIPMENT OPERATOR: GROUP 1 ALL CRANE TYPE EQUIPMENT 200 TON AND LARGER AND INCLUDING 400 TON CAPACITY CRANES. ALL TOWER CRANES | $38.09 | $57.14 | same |
| Kay County | POWER EQUIPMENT OPERATOR: GROUP 1 ALL CRANE TYPE EQUIPMENT 200 TON AND LARGER AND INCLUDING 400 TON CAPACITY CRANES. ALL TOWER CRANES | $38.09 | $57.14 | same |
| Nowata County | POWER EQUIPMENT OPERATOR: GROUP 1 ALL CRANE TYPE EQUIPMENT 200 TON AND LARGER AND INCLUDING 400 TON CAPACITY CRANES. ALL TOWER CRANES | $38.09 | $57.14 | same |
| Rogers County | POWER EQUIPMENT OPERATOR: GROUP 1 ALL CRANE TYPE EQUIPMENT 200 TON AND LARGER AND INCLUDING 400 TON CAPACITY CRANES. ALL TOWER CRANES | $38.09 | $57.14 | same |
Oklahoma operating engineer prevailing wage by county, with a map
More from DOL on this rate
- DOL wage determination
- SAM.gov wage determinations
- Davis-Bacon determinations list journeyworker rates. Apprentices in a program registered with DOL or a recognized state agency can be paid the program's percentage of the rate, within its ratio; anyone else gets the full rate (29 CFR 5.5(a)(4)).
Are you being paid this rate?
Add your base pay to the fringe your employer pays for you, in cash or into plans, and compare the sum with the total. The Department of Labor's Wage and Hour Division takes complaints: 1-866-487-9243, or dol.gov/agencies/whd/contact/complaints.
Source
U.S. Department of Labor, Wage and Hour Division (DOL), wage determination OK20260050 Mod 1, published May 18, 2026: sam.gov/wage-determination/OK20260050/1
We read every active Oklahoma Davis-Bacon wage determination from SAM.gov's own data and check every number with a second, independent read of the same file. DOL prints no total; ours is base plus fringe. How we check · Download Osage County as CSV · Report an error