Home / Michigan / Lenawee County / Operating Engineer
Lenawee County, MI · Operating Engineer
Operating Engineer prevailing wage in Lenawee County, Michigan
$73.64an hour, fringes included · 4.1 Power Equip. Operator - Commercial
One rate, fringe benefits included (LEO prints no split) · Commercial
Lenawee County uses the same operating engineer rates as 6 other counties. See all of them on one page.
On Michigan public works in Lenawee County, an operating engineer working as 4.1 power equip. operator - commercial must be paid at least $73.64 an hour. LEO prints one rate with fringe benefits included, so there is no separate base wage.
LEO county rates, November 2025 edition, effective November 1, 2025. The contracting agent gets LEO's rates before advertising and puts them in the specifications; if the contract isn't awarded or started within 90 days of LEO's determination, LEO must redetermine them (MCL 408.1103). Checked against michigan.gov on October 25, 2026.
LEO lists 17 operating engineer rates for Lenawee County, from $39.09 to $73.64 an hour. See all of them.
- LEO prints no wage/fringe split. Derived from its overtime rates (wage = 2 × (time and a half − straight time)), the split would be about $48.30 wage + $25.34 fringe. That's our estimate, not LEO's figure.
One rate, fringe benefits included: $73.64
LEO publishes a single hourly figure that already includes fringe benefits. A contractor can pay it all as wages, or pay part as contributions to bona fide benefit plans for the worker, as long as the two add up to at least $73.64. LEO doesn't publish a base and fringe split, so this page doesn't invent one.
LEO's data note: LEO prints package rates only (wage + fringe at straight time, 1.5x, 2x)
Davis-Bacon operating engineer rate in Lenawee County
Federally funded or assisted construction here uses the U.S. Department of Labor's wage determinations. Contracts that already require Davis-Bacon rates are exempt from Michigan's Act, so a Davis-Bacon job uses the federal rate (MCL 408.1102(1)).
We don't put a federal figure next to LEO's here, because the federal determinations split this trade into groups that don't line up with LEO's. The federal rows for this trade are below; match the classification to the work.
| Construction | Federal classification | Base + fringe | Base | WD |
|---|---|---|---|---|
| Building | POWER EQUIPMENT OPERATOR: GROUP 9 OILERENGI0324-019 | $60.64 | $35.29 | MI20260131 Mod 1 |
| Building | POWER EQUIPMENT OPERATOR: GROUP 8 FORKLIFT & EXTEND-A-BOOM FORKLIFTENGI0324-019 | $68.98 | $43.63 | MI20260131 Mod 1 |
| Building | POWER EQUIPMENT OPERATOR: GROUP 7 BOBCAT/SKID LOADER; LOADER;PAVER; SCRAPERENGI0324-019 | $70.69 | $45.34 | MI20260131 Mod 1 |
| Building | POWER EQUIPMENT OPERATOR: GROUP 6 REGULAR CRANE OPERATORENGI0324-019 | $71.66 | $46.31 | MI20260131 Mod 1 |
| Building | POWER EQUIPMENT OPERATOR: GROUP 5 CRANE WITH BOOM AND JIB OR LEADS 120' OR LONGERENGI0324-019 | $72.52 | $47.17 | MI20260131 Mod 1 |
| Building | POWER EQUIPMENT OPERATOR: GROUP 4 CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGERENGI0324-019 | $73.34 | $47.99 | MI20260131 Mod 1 |
| Building | POWER EQUIPMENT OPERATOR: GROUP 3 CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGERENGI0324-019 | $73.64 | $48.29 | MI20260131 Mod 1 |
| Building | POWER EQUIPMENT OPERATOR: GROUP 2 CRANE WITH BOOM AND JIB OR LEADS 300' OR LONGERENGI0324-019 | $75.14 | $49.79 | MI20260131 Mod 1 |
| Building | POWER EQUIPMENT OPERATOR: GROUP 1 CRANE WITH BOOM AND JIB OR LEADS 400' OR LONGERENGI0324-019 | $76.64 | $51.29 | MI20260131 Mod 1 |
| Building | OPERATOR: TRACTORSUMI2011-056 | $26.91 | $19.60 | MI20260131 Mod 1 |
| Building | OPERATOR: ROLLERSUMI2011-056 | $35.09 | $28.02 | MI20260131 Mod 1 |
| Building | OPERATOR: GRADER/BLADESUMI2011-056 | $30.07 | $24.04 | MI20260131 Mod 1 |
| Building | OPERATOR: BULLDOZERSUMI2011-056 | $23.56 | $22.34 | MI20260131 Mod 1 |
| Building | OPERATOR: BACKHOE/EXCAVATORSUMI2011-056 | $38.80 | $29.04 | MI20260131 Mod 1 |
| Highway | OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 18- OILER (ALCONA, ALPENA, ARENAC, BAY, CHEBOYGAN, CLARE, CLINTON, CRAWFORD, GENESEE, GLADWIN, GRATIOT, HURON, …ENGI0324-003 | $64.03 | $35.78 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 17- COMPRESSOR OR WELDER OPERATOR (ALCONA, ALPENA, ARENAC, BAY, CHEBOYGAN, CLARE, CLINTON, CRAWFORD, GENESEE, …ENGI0324-003 | $47.69 | $32.29 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 16- FORKLIFT AND 1 DRUM HOIST (ALCONA, ALPENA, ARENAC, BAY, CHEBOYGAN, CLARE, CLINTON, CRAWFORD, GENESEE, …ENGI0324-003 | $75.02 | $46.77 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 15- HOISTING OPERATOR; 2 DRUM HOIST AND RUBBER TIRED BACKHOE (ALCONA, ALPENA, ARENAC, BAY, CHEBOYGAN, CLARE, …ENGI0324-003 | $78.22 | $49.97 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 14- CRANE OPERATOR ON A CRANE THAT REQUIRES AN OILER (ALCONA, ALPENA, ARENAC, BAY, CHEBOYGAN, CLARE, CLINTON, …ENGI0324-003 | $79.86 | $51.61 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 13- CRANE OPERATOR; JOB MECHANIC AND 3 DRUM HOIST AND EXCAVATOR (ALCONA, ALPENA, ARENAC, BAY, CHEBOYGAN, …ENGI0324-003 | $78.86 | $50.61 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 12- ENGINEER WHEN OPERATING COMBINATION OF BOOM AND JIB 120' OR LONGER ON A CRANE THAT REQUIRES AN OILER …ENGI0324-003 | $80.22 | $51.97 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 11- ENGINEER WHEN OPERATING COMBINATION OF BOOM AND JIB 120' OR LONGER (ALCONA, ALPENA, ARENAC, BAY, …ENGI0324-003 | $79.22 | $50.97 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 10- TOWER CRANE & DERRICK OPERATOR (WHERE OPERATOR'S WORK STATION IS 50 FT. OR MORE ABOVE FIRST SUB-LEVEL) ON …ENGI0324-003 | $80.95 | $52.70 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 9- TOWER CRANE & DERRICK OPERATOR (WHERE OPERATOR'S WORK STATION IS 50 FT. OR MORE ABOVE FIRST SUB-LEVEL) …ENGI0324-003 | $79.95 | $51.70 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 8- ENGINEER WHEN OPERATING COMBINATION OF BOOM AND JIB 140' OR LONGER ON A CRANE THAT REQUIRES AN OILER …ENGI0324-003 | $81.40 | $53.15 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 7- ENGINEER WHEN OPERATING COMBINATION OF BOOM AND JIB 140' OR LONGER (ALCONA, ALPENA, ARENAC, BAY, CHEBOYGAN, …ENGI0324-003 | $80.40 | $52.15 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 6- ENGINEER WHEN OPERATING COMBINATION OF BOOM AND JIB 220' OR LONGER ON A CRANE THAT REQUIRES AN OILER …ENGI0324-003 | $81.67 | $53.42 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 5- ENGINEER WHEN OPERATING COMBINATION OF BOOM AND JIB 220' OR LONGER (ALCONA, ALPENA, ARENAC, BAY, CHEBOYGAN, …ENGI0324-003 | $80.67 | $52.42 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 4- ENGINEER WHEN OPERATING COMBINATION OF BOOM AND JIB 300' OR LONGER ON A CRANE THAT REQUIRES AN OILER …ENGI0324-003 | $83.17 | $54.92 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 3- ENGINEER WHEN OPERATING COMBINATION OF BOOM AND JIB 300' OR LONGER (ALCONA, ALPENA, ARENAC, BAY, CHEBOYGAN, …ENGI0324-003 | $82.17 | $53.92 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 2- ENGINEER WHEN OPERATING COMBINATION OF BOOM AND JIB 400' OR LONGER ON A CRANE THAT REQUIRES AN OILER …ENGI0324-003 | $84.67 | $56.42 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, STEEL ERECTION: GROUP 1- ENGINEER WHEN OPERATING COMBINATION OF BOOM AND JIB 400' OR LONGER (ALCONA, ALPENA, ARENAC, BAY, CHEBOYGAN, …ENGI0324-003 | $83.67 | $55.42 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, UNDERGROUND CONSTRUCTION (INCLUDING SEWER): GROUP 5- FIRE PERSON, OILER (AREA 2: ALCONA, ALLEGAN, ALGER, ALPENA, ANTRIM, ARENAC, …ENGI0324-005 | $42.45 | $30.35 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, UNDERGROUND CONSTRUCTION (INCLUDING SEWER): GROUP 3- AIR COMPRESSORS (600 CFM OR LARGER); AIR COMPRESSORS (2 OR MORE-LESS THAN 600 …ENGI0324-005 | $65.77 | $40.52 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, UNDERGROUND CONSTRUCTION (INCLUDING SEWER): GROUP 1- BACKFILLER TAMPER; BACKHOE; BATCH PLANT OPERATOR (CONCRETE); CLAMSHELL; …ENGI0324-005 | $71.23 | $45.98 | MI20260001 Mod 3 |
| Highway | POWER EQUIPMENT OPERATORS:, AIRPORT, BRIDGE & HIGHWAY CONSTRUCTION: GROUP 2- ASPHALT PLANT OPERATOR; CRANE OPERATOR (DOES NOT INCLUDE WORK ON BRIDGE …ENGI0324-006 | $70.31 | $45.06 | MI20260001 Mod 3 |
| Highway | POWER EQUIPMENT OPERATORS:, AIRPORT, BRIDGE & HIGHWAY CONSTRUCTION: GROUP 1- PAVER OPERATOR (5 BAGS OR MORE); SLIP FORM PAVER; ASPHALT PAVER (SELF-PROPELLED); …ENGI0324-006 | $71.46 | $46.21 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, SEWER RELINING: GROUP 2- OPERATION OF HOT WATER HEATERS AND CIRCULATION SYSTEMS, WATER JETTERS AND VACUUM AND MECHANICAL DEBRIS …ENGI0324-008 | $50.77 | $35.33 | MI20260001 Mod 3 |
| Highway | OPERATOR: POWER EQUIPMENT, SEWER RELINING: GROUP 1- OPERATION OF AUDIO-VISUAL CLOSED CIRCUIT TV SYSTEM, INCLUDING REMOTE IN-GROUND CUTTER AND OTHER EQUIPMENT …ENGI0324-008 | $52.81 | $37.37 | MI20260001 Mod 3 |
| Highway | POWER EQUIPMENT OPERATORS - GAS DISTRIBUTION AND DUCT INSTALLATION WORK: GROUP 2- DOZER (LESS THAN D-6 EQUIVALENT), ENDLOADER (UNDER 2 YD. CAPACITY), SIDE BOOM …ENGI0325-012 | $61.30 | $36.05 | MI20260001 Mod 3 |
The first 40 of 99 federal rows; every row is in the determinations linked above.
Davis-Bacon rates from SAM.gov, read October 25, 2026. Our federal totals are base plus fringe; DOL prints no total. Michigan Davis-Bacon changes
When this rate changes
- A contract keeps the rates LEO determined for it, unless it isn't awarded or started within 90 days, when LEO redetermines them (MCL 408.1103).
- LEO publishes a new edition every November 1. This page copies the November 2025 edition; Barry, Bay, Benzie and Berrien carry 2026 corrections.
Every operating engineer rate in Lenawee County
As LEO lists them. The highlighted row is the one this page leads with.
- 4.1 Power Equip. Operator - CommercialCommercial$73.64
- 4.2 Power Equip. Operator - CommercialCommercial$73.34
- 4.3 Power Equip. Operator - CommercialCommercial$72.52
- 4.4 Power Equip. Operator - CommercialCommercial$71.66
- 3.1 Power Equip. Operator - Highway & HeavyHighway & Heavy$71.46
- 4.5 Power Equip. Operator - CommercialCommercial$70.69
- 3.2 Power Equip. Operator - Highway & HeavyHighway & Heavy$70.31
- Boom Truck$70.31
- 4.6 Power Equip. Operator - CommercialCommercial$68.98
- 3.3 Power Equip. Operator - Highway & HeavyHighway & Heavy$63.58
- 3.4 Power Equip. Operator - Highway & HeavyHighway & Heavy$63.02
- Articulated Hauler$63.02
- Off-Road Truck$63.02
- 4.7 Power Equip. Operator - CommercialCommercial$61.67
- 4.8 Power Equip. Operator - commercialCommercial$60.64
- 3.5 Power Equip. Operator - Highway & HeavyHighway & Heavy$44.80
- Landscaping equipment$39.09
| Classification | Total (fringes included) | Base | Fringe benefits | Effective |
|---|---|---|---|---|
| 3.1 Power Equip. Operator - Highway & HeavyHighway & Heavy | $71.46 | incl. | incl. | Nov 1, 2025 |
| 3.2 Power Equip. Operator - Highway & HeavyHighway & Heavy | $70.31 | incl. | incl. | Nov 1, 2025 |
| 3.3 Power Equip. Operator - Highway & HeavyHighway & Heavy | $63.58 | incl. | incl. | Nov 1, 2025 |
| 3.4 Power Equip. Operator - Highway & HeavyHighway & Heavy | $63.02 | incl. | incl. | Nov 1, 2025 |
| 3.5 Power Equip. Operator - Highway & HeavyHighway & Heavy | $44.80 | incl. | incl. | Nov 1, 2025 |
| 4.1 Power Equip. Operator - CommercialCommercial | $73.64 | incl. | incl. | Nov 1, 2025 |
| 4.2 Power Equip. Operator - CommercialCommercial | $73.34 | incl. | incl. | Nov 1, 2025 |
| 4.3 Power Equip. Operator - CommercialCommercial | $72.52 | incl. | incl. | Nov 1, 2025 |
| 4.4 Power Equip. Operator - CommercialCommercial | $71.66 | incl. | incl. | Nov 1, 2025 |
| 4.5 Power Equip. Operator - CommercialCommercial | $70.69 | incl. | incl. | Nov 1, 2025 |
| 4.6 Power Equip. Operator - CommercialCommercial | $68.98 | incl. | incl. | Nov 1, 2025 |
| 4.7 Power Equip. Operator - CommercialCommercial | $61.67 | incl. | incl. | Nov 1, 2025 |
| 4.8 Power Equip. Operator - commercialCommercial | $60.64 | incl. | incl. | Nov 1, 2025 |
| Articulated Hauler | $63.02 | incl. | incl. | Oct 28, 2025 |
| Boom Truck | $70.31 | incl. | incl. | Oct 28, 2025 |
| Landscaping equipment | $39.09 | incl. | incl. | Oct 28, 2025 |
| Off-Road Truck | $63.02 | incl. | incl. | Oct 29, 2025 |
How Lenawee County compares
The main operating engineer rate in every county that has one. All bars use the same scale.
Every county in Michigan
Rates nearby
- Lenawee Countyfringes included$73.64
- Hillsdale Countyfringes included$71.22
- Monroe Countyfringes included$73.64
- Washtenaw Countyfringes included$73.64
Operating Engineer rates in nearby counties
Current LEO rates. LEO sets rates county by county from local union agreements, so neighbouring counties in one agreement's area often match.
LEO's operating engineer rates for Lenawee County are the same as in 6 other counties: Macomb, Monroe, Oakland, St. Clair, Washtenaw, Wayne.
| County | Classification | Total (fringes included) | Base | vs Lenawee County |
|---|---|---|---|---|
| Lenawee County | 4.1 Power Equip. Operator - Commercial | $73.64 | incl. | |
| Monroe County | 4.1 Power Equip. Operator - Commercial | $73.64 | incl. | same |
| Washtenaw County | 4.1 Power Equip. Operator - Commercial | $73.64 | incl. | same |
| Wayne County | 4.1 Power Equip. Operator - Commercial | $73.64 | incl. | same |
| Hillsdale County | 4.1 Power Equip. Operator - Commercial | $71.22 | incl. | −$2.42 |
| Jackson County | 4.1 Power Equip. Operator - Commercial | $71.22 | incl. | −$2.42 |
| Livingston County | 4.1 Power Equip. Operator - Commercial | $71.22 | incl. | −$2.42 |
Michigan operating engineer prevailing wage by county, with a map
More from LEO on this rate
- LEO county rate schedule, page 6
- LEO's prevailing wages by county
- LEO's county PDF lists apprentice rates by level for each classification; see the PDF linked on each page (LEO).
Are you being paid this rate?
LEO's rate is wage and fringe together: add your hourly wage to what your employer pays into benefit plans for you and compare the sum with the total. LEO Wage and Hour Division, P.O. Box 30476, Lansing, MI 48909 (LEO).
Source
Department of Labor and Economic Opportunity (LEO), county rate schedule LEO-November-2025-lenawee, effective November 1, 2025, page 6: www.michigan.gov/leo/-/media/Project/Websites/leo/Documents/PWRS-By-County/Lenawee.pdf
We read every county PDF in LEO's November 2025 edition and check every page with a second, separate read; the last run found no mismatches. Where LEO prints the same classification twice in a county without saying where each applies, both rows are shown. How we check · Download Lenawee County as CSV · Report an error