Home / Nebraska / Nance County / Operating Engineer

Nance County, NE · Operating Engineer

Operating Engineer prevailing wage in Nance County, Nebraska

$24.04an hour, base + fringe

$21.82 wage + $2.22 fringe benefits · Building · SUNE2012-017

On federally funded or assisted building construction in Nance County, an operating engineer must be paid at least $24.04 an hour: a $21.82 base wage plus $2.22 in fringe benefits, under wage determination NE20260080 (modification 1). DOL prints no total, so $24.04 is our sum of the two.

Wage determination NE20260080, modification 1, published May 18, 2026, for building construction; rate identifier SUNE2012-017 (April 19, 2012). Checked against sam.gov on October 25, 2026.

Nebraska has no state wage schedule; Davis-Bacon applies to federally funded work. Bidders on state work file a statement that they follow "fair labor standards" (Neb. Rev. Stat. 73-104), but no agency publishes rates.

DOL lists 26 operating engineer rates for Nance County, from $10.05 to $51.93 an hour. See all of them.

Base wage and fringe benefits: $21.82 + $2.22

The base wage is the taxable hourly wage. DOL prints the fringe benefits as one hourly figure, not itemized; it can go to health, pension, vacation and training plans, or be paid as cash where the state allows.

Base wage (taxable)$21.82
Fringe benefits (one figure, not itemized)$2.22
Base + fringe benefits (our sum; DOL prints no total)$24.04

When this rate changes

Every operating engineer rate in Nance County

As DOL lists them. The highlighted row is the one this page leads with.

ClassificationBase + fringeBaseFringe benefitsWD
OPERATOR: LOADERBuildingSUNE2012-017$17.52 $16.58 $0.94 NE20260080 Mod 1
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOEBuildingSUNE2012-017$24.04 $21.82 $2.22 NE20260080 Mod 1
OPERATOR: TRENCHERHighwayENGI0571-005$51.93 $32.18 $19.75 NE20260031 Mod 1
POWER EQUIPMENT OPERATOR: BACKHOE, EXCAVATOR, TRACKHOE (ADAMS, BLAINE, BUFFALO, CLAY, CUSTER, FRANKLIN, GARFIELD, GREELEY, HALL, HAMILTON, HOWARD, KEARNEY, LOUP, MERRICK, NANCE, NUCKOLLS, PHELPS, SHERMAN, VALLEY, WEBSTER, WHEELER)HighwaySUNE2011-027$15.14 $15.14 $0.00 NE20260031 Mod 1
OPERATOR: GRADER/BLADE (BLAINE, BUFFALO, CUSTER, CLAY, FRANKLIN, GARFIELD, GREELEY, HAMILTON, HOWARD, KEARNEY, LOUP, MERRICK, NANCE, NUCKOLLS, PHELPS, SHERMAN, WEBSTER & WHEELER COUNTIES)HighwaySUNE2011-027$15.51 $15.51 $0.00 NE20260031 Mod 1
OPERATOR: TRACTOR (ADAMS, BLAINE, BUFFALO, CUSTER, CLAY, FRANKLIN, GARFIELD, GREELEY, HAMILTON, HARLAND, HOWARD, KEARNEY, LOUP, MERRICK, NANCE, NUCKOLLS, PHELPS, SHERMAN, VALLEY WEBSTER, & WHEELE COUNTIES)HighwaySUNE2011-027$12.80 $12.80 $0.00 NE20260031 Mod 1
OPERATOR: SCREEDHighwaySUNE2011-027$12.01 $12.01 $0.00 NE20260031 Mod 1
OPERATOR: SCRAPER (ADAMS, BLAINE, BUFFALO, CUSTER, CLAY, FRANKLIN, GARFIELD, GREELEY, HALL, HAMILTON, HOWARD, KEARNEY, LOUP, MERRICK, NANCE, NUCKOLLS, PHELPS, SHERMAN, VALLEY WEBSTER, & WHEELE COUNTIES)HighwaySUNE2011-027$15.79 $15.79 $0.00 NE20260031 Mod 1
OPERATOR: ROLLER (BLAINE, BUFFALO, CUSTER, CLAY, FRANKLIN, GARFIELD, GREELEY, HALL, HAMILTON, HOWARD, KEARNEY, LOUP, MERRICK, NANCE, NUCKOLLS, PHELPS, SHERMAN, WEBSTER, & WHEELE COUNTIES)HighwaySUNE2011-027$12.00 $12.00 $0.00 NE20260031 Mod 1
OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE)HighwaySUNE2011-027$12.35 $12.35 $0.00 NE20260031 Mod 1
OPERATOR: MECHANIC (ADAMS, BLAINE, BUFFALO, CUSTER, CLAY, FRANKLIN, GARFIELD, GREELEY, HAMILTON, HARLAND, HOWARD, KEARNEY, LOUP, MERRICK, NANCE, NUCKOLLS, PHELPS, SHERMAN, VALLEY WEBSTER, & WHEELE COUNTIES)HighwaySUNE2011-027$15.42 $15.42 $0.00 NE20260031 Mod 1
OPERATOR: LOADER (ADAMS, BLAINE, CLAY, FRANKLIN, GARFIELD, GREELEY, HAMILTON, HOWARD, KEARNEY, LOUP, MARRICK, NANCE, NUCKOLLS, PHELPS, SHERMAN, VALLEY, WEBSTER, WHEELER COUNTIES)HighwaySUNE2011-027$14.68 $14.68 $0.00 NE20260031 Mod 1
OPERATOR: DISTRIBUTORHighwaySUNE2011-027$14.37 $14.37 $0.00 NE20260031 Mod 1
OPERATOR: CRANE (ADAMS, BLAINE, BUFFALO, CUSTER, CLAY, FRANKLIN, GARFIELD, GREELEY, HALL, HAMILTON, HOWARD, KEARNEY, LOUP, MERRICK, NANCE, NUCKOLLS, PHELPS, SHERMAN, VALLEY WEBSTER, & WHEELE COUNTIES)HighwaySUNE2011-027$16.17 $16.17 $0.00 NE20260031 Mod 1
OPERATOR: COMPACTORHighwaySUNE2011-027$10.05 $10.05 $0.00 NE20260031 Mod 1
OPERATOR: CHAIN SAWHighwaySUNE2011-027$13.35 $13.35 $0.00 NE20260031 Mod 1
OPERATOR: BULLDOZERHighwaySUNE2011-027$15.69 $15.69 $0.00 NE20260031 Mod 1
OPERATOR: BROOM/SWEEPERHighwaySUNE2011-027$10.77 $10.77 $0.00 NE20260031 Mod 1
OPERATOR: BACKHOE LOADER COMBOHighwaySUNE2011-027$14.33 $14.33 $0.00 NE20260031 Mod 1
OPERATOR: ASPHALT PLANTHighwaySUNE2011-027$12.75 $12.75 $0.00 NE20260031 Mod 1
OPERATING ENGINEERS: (SKID LOADER)HighwaySUNE2011-027$12.96 $12.96 $0.00 NE20260031 Mod 1
OPERATOR: SCRAPERHeavySUNE2011-008$16.95 $14.89 $2.06 NE20260041 Mod 1
OPERATOR: LOADERHeavySUNE2011-008$16.73 $15.54 $1.19 NE20260041 Mod 1
OPERATOR: BULLDOZERHeavySUNE2011-008$18.99 $15.95 $3.04 NE20260041 Mod 1
OPERATOR: BOBCAT/SKID STEER/SKID LOADERHeavySUNE2011-008$23.54 $19.47 $4.07 NE20260041 Mod 1
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOEHeavySUNE2011-008$22.57 $19.96 $2.61 NE20260041 Mod 1

How Nance County compares

The main operating engineer rate in every county that has one, and how the pay splits here and nearby. All bars use the same scale.

Every county in Nebraska

$23.08Arthur$28.27Douglas
NanceNearby: Merrick $24.04, Boone $24.04, Seward $25.61Each column is a group of counties with about the same main rate; its height is how many. 9 counties pay more than Nance, 53 the same, 30 less.

Wage and fringe benefits, nearby

  1. Nance Countybase $21.82$24.04
  2. Merrick Countybase $21.82$24.04
  3. Boone Countybase $21.82$24.04
  4. Seward Countybase $20.68$25.61

Operating Engineer rates in nearby counties

Current DOL rates. Davis-Bacon rates are set for groups of counties, so neighbours often share them; the county where the work is done decides.

CountyClassificationBase + fringeBasevs Nance County
Nance CountyOPERATOR: BACKHOE/EXCAVATOR/TRACKHOE$24.04 $21.82 
Merrick CountyOPERATOR: BACKHOE/EXCAVATOR/TRACKHOE$24.04 $21.82 same
Boone CountyOPERATOR: BACKHOE/EXCAVATOR/TRACKHOE$24.04 $21.82 same
Polk CountyOPERATOR: BACKHOE/EXCAVATOR/TRACKHOE$24.04 $21.82 same
Platte CountyOPERATOR: BACKHOE/EXCAVATOR/TRACKHOE$24.04 $21.82 same
Howard CountyOPERATOR: BACKHOE/EXCAVATOR/TRACKHOE$24.04 $21.82 same
Greeley CountyOPERATOR: BACKHOE/EXCAVATOR/TRACKHOE$24.04 $21.82 same

Nebraska operating engineer prevailing wage by county, with a map

More from DOL on this rate

All Nance County prevailing wage rates

Are you being paid this rate?

Add your base pay to the fringe your employer pays for you, in cash or into plans, and compare the sum with the total. The Department of Labor's Wage and Hour Division takes complaints: 1-866-487-9243, or dol.gov/agencies/whd/contact/complaints.

Source

U.S. Department of Labor, Wage and Hour Division (DOL), wage determination NE20260080 Mod 1, published May 18, 2026: sam.gov/wage-determination/NE20260080/1

We read every active Nebraska Davis-Bacon wage determination from SAM.gov's own data and check every number with a second, independent read of the same file. DOL prints no total; ours is base plus fringe. How we check · Download Nance County as CSV · Report an error