Home / Ohio / Allen County / Painter
Allen County, OH · Painter
Painter prevailing wage in Allen County, Ohio
$25.79an hour, base + fringe
$24.54 wage + $1.25 fringe benefits · Building · SUOH2012-070
On federally funded or assisted building construction in Allen County, a painter must be paid at least $25.79 an hour: a $24.54 base wage plus $1.25 in fringe benefits, under wage determination OH20260068 (modification 1). DOL prints no total, so $25.79 is our sum of the two.
Wage determination OH20260068, modification 1, published May 18, 2026, for building construction; rate identifier SUOH2012-070 (August 29, 2014). Checked against sam.gov on October 25, 2026.
Ohio also sets its own rates (ORC 4115, Department of Commerce); on jobs covered by both, pay the higher. Ohio's rates sit behind an OHID login on its prevailing wage portal, so this site shows the Davis-Bacon rates only.
DOL lists 14 painter rates for Allen County, from $24.11 to $54.15 an hour. See all of them.
Base wage and fringe benefits: $24.54 + $1.25
The base wage is the taxable hourly wage. DOL prints the fringe benefits as one hourly figure, not itemized; it can go to health, pension, vacation and training plans, or be paid as cash where the state allows.
| Base wage (taxable) | $24.54 |
| Fringe benefits (one figure, not itemized) | $1.25 |
| Base + fringe benefits (our sum; DOL prints no total) | $25.79 |
When this rate changes
- A contract keeps the wage determination in its bid documents. Modifications published before bid opening apply to it, though one published less than 10 days before can be left out if the agency finds there isn't time to tell bidders (29 CFR 1.6(c)).
- DOL changes a WD by publishing a numbered modification on SAM.gov. This page reads the modification named in the Source line; the Ohio change log lists what each one changed.
Every painter rate in Allen County
As DOL lists them. The highlighted row is the one this page leads with.
- PAINTER: BRUSH AND ROLLERResidential · PAIN0707-001$54.15
- PAINTER: GROUP 4- SPRAY, EXCEPT BAR JOIST/DECK (COLUMBIANA, MAHONING, AND TRUMBULL COUNITES)Highway, Heavy · PAIN0476-001$49.50
- PAINTER- COMMERCIAL REPAINT GROUP 3- SPRAY PAINTINGHighway, Heavy · PAIN0006-002$48.90
- PAINTER: STRUCTURAL STEEL (ASHLAND, CRAWFORD, ERIE, HANCOCK, HURON, MARION, MORROW, OTTAWA (ALLEN, BAY, BONO, CATAWBA ISLAND, CLAY CENTER, CURTICE, DANBURY, EAGLE BEACH, ELLISTON, ELMORE, ERIE, FISHBACK, GEM BEACH & GENOA), RICHLAND, SANDUSKY, SENECA & WYANDOT) WINTER REPAINT: BETWEEN DECEMBER 1 TO MARCH 31 - 90%JR $.50 PER HOUR SHALL BE ADDED TO THE RATE OF PAY FOR THE CLASSIFICATION OF WORK: WHILE WORKING SWINGSTAGE, BOATSWAIN CHAIR, NEEDLE BEAM AND HORIZONTAL CABLE. WHILE OPERATING SPRAYGUNS, SANDBLASTING, COBBLASTING AND HIGH PRESSURE WATERBLASTING (4000PSI). $1.00 PER HOUR SHALL BE ADDED TO THE RATE OF PAY FOR THE CLASSIFICATION OF WORK: FOR THE APPLICATION OF CATALIZED EPOXY, INCLUDING LATEX EPOXY THAT IS DEEMED HAZARDOUS, LEAD ABATEMENT, OR FOR WORK OR MATERIAL WHERE SPECIAL PRECAUTIONS BEYOND NORMAL WORK DUTIES MUST BE TAKEN. FOR WORKING ON STACKS, TANKS, AND TOWERS OVER 40 FEET IN HEIGHTHighway, Heavy · PAIN0788-002$48.25
- PAINTER: LEAD ABATEMENT (ALLEN, AUGLAIZE, CHAMPAIGN, DEFIANCE, HARDIN, LOGAN, MERCER, PAULDING, PUTNAM, SHELBY, VAN WERT, AND WILLIAMS COUNTIES) ALL SURFACES 40 FT. OR OVER WHERE MATERIAL IS APPLIED TO OR LABOR PERFORMED ON, ABOVE GROUND LEVEL (EXTERIOR), FLOOR LEVEL (INTERIOR) - $.50 PREMIUM APPLYING COAL TAR PRODUCTS - $1.00 PREMIUMHighway, Heavy · PAIN1020-002$47.88
- PAINTER: DRYWALL FINISHING & TAPING (ALLEN, AUGLAIZE, CHAMPAIGN, DEFIANCE, HARDIN, LOGAN, MERCER, PAULDING, PUTNAM, SHELBY, VAN WERT, AND WILLIAMS COUNTIES): LL SURFACES 40 FT. OR OVER WHERE MATERIAL IS APPLIED TO OR LABOR PERFORMED ON, ABOVE GROUND LEVEL (EXTERIOR), FLOOR LEVEL (INTERIOR) - $.50 PREMIUM APPLYING COAL TAR PRODUCTS - $1.00 PREMIUMHighway, Heavy · PAIN1020-002$46.88
- PAINTER: SPRAY, SANDBLASTING PRESSURE CLEANING, & REFINERY (ALLEN, AUGLAIZE, CHAMPAIGN, DEFIANCE, HARDIN, LOGAN, MERCER, PAULDING, PUTNAM, SHELBY, VAN WERT, AND WILLIAMS COUNTIES) ALL SURFACES 40 FT. OR OVER WHERE MATERIAL IS APPLIED TO OR LABOR PERFORMED ON, ABOVE GROUND LEVEL (EXTERIOR), FLOOR LEVEL (INTERIOR) - $.50 PREMIUM APPLYING COAL TAR PRODUCTS - $1.00 PREMIUMHighway, Heavy · PAIN1020-002$46.88
- PAINTER: WALLCOVERINGS (ALLEN, AUGLAIZE, CHAMPAIGN, DEFIANCE, HARDIN, LOGAN, MERCER, PAULDING, PUTNAM, SHELBY, VAN WERT, AND WILLIAMS COUNTIES) ALL SURFACES 40 FT. OR OVER WHERE MATERIAL IS APPLIED TO OR LABOR PERFORMED ON, ABOVE GROUND LEVEL (EXTERIOR), FLOOR LEVEL (INTERIOR) - $.50 PREMIUM APPLYING COAL TAR PRODUCTS - $1.00 PREMIUMHighway, Heavy · PAIN1020-002$46.88
- PAINTER: BRUSH & ROLLER (ASHLAND, CRAWFORD, ERIE, HANCOCK, HURON, MARION, MORROW, OTTAWA (ALLEN, BAY, BONO, CATAWBA ISLAND, CLAY CENTER, CURTICE, DANBURY, EAGLE BEACH, ELLISTON, ELMORE, ERIE, FISHBACK, GEM BEACH & GENOA), RICHLAND, SANDUSKY, SENECA & WYANDOT) WINTER REPAINT: BETWEEN DECEMBER 1 TO MARCH 31 - 90%JR $.50 PER HOUR SHALL BE ADDED TO THE RATE OF PAY FOR THE CLASSIFICATION OF WORK: WHILE WORKING SWINGSTAGE, BOATSWAIN CHAIR, NEEDLE BEAM AND HORIZONTAL CABLE. WHILE OPERATING SPRAYGUNS, SANDBLASTING, COBBLASTING AND HIGH PRESSURE WATERBLASTING (4000PSI). $1.00 PER HOUR SHALL BE ADDED TO THE RATE OF PAY FOR THE CLASSIFICATION OF WORK: FOR THE APPLICATION OF CATALIZED EPOXY, INCLUDING LATEX EPOXY THAT IS DEEMED HAZARDOUS, LEAD ABATEMENT, OR FOR WORK OR MATERIAL WHERE SPECIAL PRECAUTIONS BEYOND NORMAL WORK DUTIES MUST BE TAKEN. FOR WORKING ON STACKS, TANKS, AND TOWERS OVER 40 FEET IN HEIGHTHighway, Heavy · PAIN0788-002$46.65
- PAINTER: SWING STAGE, CHAIR, SPIDERS, & CHERRY PICKERS (ALLEN, AUGLAIZE, CHAMPAIGN, DEFIANCE, HARDIN, LOGAN, MERCER, PAULDING, PUTNAM, SHELBY, VAN WERT, AND WILLIAMS COUNTIES) ALL SURFACES 40 FT. OR OVER WHERE MATERIAL IS APPLIED TO OR LABOR PERFORMED ON, ABOVE GROUND LEVEL (EXTERIOR), FLOOR LEVEL (INTERIOR) - $.50 PREMIUM APPLYING COAL TAR PRODUCTS - $1.00 PREMIUMHighway, Heavy · PAIN1020-002$46.38
- PAINTER: BRUSH & ROLLER (ALLEN, AUGLAIZE, CHAMPAIGN, DEFIANCE, HARDIN, LOGAN, MERCER, PAULDING, PUTNAM, SHELBY, VAN WERT, AND WILLIAMS COUNTIES) ALL SURFACES 40 FT. OR OVER WHERE MATERIAL IS APPLIED TO OR LABOR PERFORMED ON, ABOVE GROUND LEVEL (EXTERIOR), FLOOR LEVEL (INTERIOR) - $.50 PREMIUM APPLYING COAL TAR PRODUCTS - $1.00 PREMIUMHighway, Heavy · PAIN1020-002$46.13
- PAINTER: SPRAYBuilding · SUOH2012-070$35.18
- PAINTER (BRUSH AND ROLLER)Building · SUOH2012-070$25.79
- SIGN PAINTER & ERECTORHighway, Heavy · PAIN0639-001$24.11
| Classification | Base + fringe | Base | Fringe benefits | WD |
|---|---|---|---|---|
| PAINTER: SPRAYBuildingSUOH2012-070 | $35.18 | $22.78 | $12.40 | OH20260068 Mod 1 |
| PAINTER (BRUSH AND ROLLER)BuildingSUOH2012-070 | $25.79 | $24.54 | $1.25 | OH20260068 Mod 1 |
| PAINTER- COMMERCIAL REPAINT GROUP 3- SPRAY PAINTINGHighway, HeavyPAIN0006-002 | $48.90 | $29.95 | $18.95 | OH20260001 Mod 5 |
| PAINTER: GROUP 4- SPRAY, EXCEPT BAR JOIST/DECK (COLUMBIANA, MAHONING, AND TRUMBULL COUNITES)Highway, HeavyPAIN0476-001 | $49.50 | $31.14 | $18.36 | OH20260001 Mod 5 |
| SIGN PAINTER & ERECTORHighway, HeavyPAIN0639-001 | $24.11 | $20.61 | $3.50 | OH20260001 Mod 5 |
| PAINTER: BRUSH & ROLLER (ASHLAND, CRAWFORD, ERIE, HANCOCK, HURON, MARION, MORROW, OTTAWA (ALLEN, BAY, BONO, CATAWBA ISLAND, CLAY CENTER, CURTICE, DANBURY, EAGLE BEACH, ELLISTON, ELMORE, ERIE, FISHBACK, GEM BEACH & GENOA), RICHLAND, SANDUSKY, SENECA & WYANDOT) WINTER REPAINT: BETWEEN DECEMBER 1 TO MARCH 31 - 90%JR $.50 PER HOUR SHALL BE ADDED TO THE RATE OF PAY FOR THE CLASSIFICATION OF WORK: WHILE WORKING SWINGSTAGE, BOATSWAIN CHAIR, NEEDLE BEAM AND HORIZONTAL CABLE. WHILE OPERATING SPRAYGUNS, SANDBLASTING, COBBLASTING AND HIGH PRESSURE WATERBLASTING (4000PSI). $1.00 PER HOUR SHALL BE ADDED TO THE RATE OF PAY FOR THE CLASSIFICATION OF WORK: FOR THE APPLICATION OF CATALIZED EPOXY, INCLUDING LATEX EPOXY THAT IS DEEMED HAZARDOUS, LEAD ABATEMENT, OR FOR WORK OR MATERIAL WHERE SPECIAL PRECAUTIONS BEYOND NORMAL WORK DUTIES MUST BE TAKEN. FOR WORKING ON STACKS, TANKS, AND TOWERS OVER 40 FEET IN HEIGHTHighway, HeavyPAIN0788-002 | $46.65 | $29.13 | $17.52 | OH20260001 Mod 5 |
| PAINTER: STRUCTURAL STEEL (ASHLAND, CRAWFORD, ERIE, HANCOCK, HURON, MARION, MORROW, OTTAWA (ALLEN, BAY, BONO, CATAWBA ISLAND, CLAY CENTER, CURTICE, DANBURY, EAGLE BEACH, ELLISTON, ELMORE, ERIE, FISHBACK, GEM BEACH & GENOA), RICHLAND, SANDUSKY, SENECA & WYANDOT) WINTER REPAINT: BETWEEN DECEMBER 1 TO MARCH 31 - 90%JR $.50 PER HOUR SHALL BE ADDED TO THE RATE OF PAY FOR THE CLASSIFICATION OF WORK: WHILE WORKING SWINGSTAGE, BOATSWAIN CHAIR, NEEDLE BEAM AND HORIZONTAL CABLE. WHILE OPERATING SPRAYGUNS, SANDBLASTING, COBBLASTING AND HIGH PRESSURE WATERBLASTING (4000PSI). $1.00 PER HOUR SHALL BE ADDED TO THE RATE OF PAY FOR THE CLASSIFICATION OF WORK: FOR THE APPLICATION OF CATALIZED EPOXY, INCLUDING LATEX EPOXY THAT IS DEEMED HAZARDOUS, LEAD ABATEMENT, OR FOR WORK OR MATERIAL WHERE SPECIAL PRECAUTIONS BEYOND NORMAL WORK DUTIES MUST BE TAKEN. FOR WORKING ON STACKS, TANKS, AND TOWERS OVER 40 FEET IN HEIGHTHighway, HeavyPAIN0788-002 | $48.25 | $30.73 | $17.52 | OH20260001 Mod 5 |
| PAINTER: BRUSH & ROLLER (ALLEN, AUGLAIZE, CHAMPAIGN, DEFIANCE, HARDIN, LOGAN, MERCER, PAULDING, PUTNAM, SHELBY, VAN WERT, AND WILLIAMS COUNTIES) ALL SURFACES 40 FT. OR OVER WHERE MATERIAL IS APPLIED TO OR LABOR PERFORMED ON, ABOVE GROUND LEVEL (EXTERIOR), FLOOR LEVEL (INTERIOR) - $.50 PREMIUM APPLYING COAL TAR PRODUCTS - $1.00 PREMIUMHighway, HeavyPAIN1020-002 | $46.13 | $27.59 | $18.54 | OH20260001 Mod 5 |
| PAINTER: DRYWALL FINISHING & TAPING (ALLEN, AUGLAIZE, CHAMPAIGN, DEFIANCE, HARDIN, LOGAN, MERCER, PAULDING, PUTNAM, SHELBY, VAN WERT, AND WILLIAMS COUNTIES): LL SURFACES 40 FT. OR OVER WHERE MATERIAL IS APPLIED TO OR LABOR PERFORMED ON, ABOVE GROUND LEVEL (EXTERIOR), FLOOR LEVEL (INTERIOR) - $.50 PREMIUM APPLYING COAL TAR PRODUCTS - $1.00 PREMIUMHighway, HeavyPAIN1020-002 | $46.88 | $28.34 | $18.54 | OH20260001 Mod 5 |
| PAINTER: LEAD ABATEMENT (ALLEN, AUGLAIZE, CHAMPAIGN, DEFIANCE, HARDIN, LOGAN, MERCER, PAULDING, PUTNAM, SHELBY, VAN WERT, AND WILLIAMS COUNTIES) ALL SURFACES 40 FT. OR OVER WHERE MATERIAL IS APPLIED TO OR LABOR PERFORMED ON, ABOVE GROUND LEVEL (EXTERIOR), FLOOR LEVEL (INTERIOR) - $.50 PREMIUM APPLYING COAL TAR PRODUCTS - $1.00 PREMIUMHighway, HeavyPAIN1020-002 | $47.88 | $29.34 | $18.54 | OH20260001 Mod 5 |
| PAINTER: SPRAY, SANDBLASTING PRESSURE CLEANING, & REFINERY (ALLEN, AUGLAIZE, CHAMPAIGN, DEFIANCE, HARDIN, LOGAN, MERCER, PAULDING, PUTNAM, SHELBY, VAN WERT, AND WILLIAMS COUNTIES) ALL SURFACES 40 FT. OR OVER WHERE MATERIAL IS APPLIED TO OR LABOR PERFORMED ON, ABOVE GROUND LEVEL (EXTERIOR), FLOOR LEVEL (INTERIOR) - $.50 PREMIUM APPLYING COAL TAR PRODUCTS - $1.00 PREMIUMHighway, HeavyPAIN1020-002 | $46.88 | $28.34 | $18.54 | OH20260001 Mod 5 |
| PAINTER: SWING STAGE, CHAIR, SPIDERS, & CHERRY PICKERS (ALLEN, AUGLAIZE, CHAMPAIGN, DEFIANCE, HARDIN, LOGAN, MERCER, PAULDING, PUTNAM, SHELBY, VAN WERT, AND WILLIAMS COUNTIES) ALL SURFACES 40 FT. OR OVER WHERE MATERIAL IS APPLIED TO OR LABOR PERFORMED ON, ABOVE GROUND LEVEL (EXTERIOR), FLOOR LEVEL (INTERIOR) - $.50 PREMIUM APPLYING COAL TAR PRODUCTS - $1.00 PREMIUMHighway, HeavyPAIN1020-002 | $46.38 | $27.84 | $18.54 | OH20260001 Mod 5 |
| PAINTER: WALLCOVERINGS (ALLEN, AUGLAIZE, CHAMPAIGN, DEFIANCE, HARDIN, LOGAN, MERCER, PAULDING, PUTNAM, SHELBY, VAN WERT, AND WILLIAMS COUNTIES) ALL SURFACES 40 FT. OR OVER WHERE MATERIAL IS APPLIED TO OR LABOR PERFORMED ON, ABOVE GROUND LEVEL (EXTERIOR), FLOOR LEVEL (INTERIOR) - $.50 PREMIUM APPLYING COAL TAR PRODUCTS - $1.00 PREMIUMHighway, HeavyPAIN1020-002 | $46.88 | $28.34 | $18.54 | OH20260001 Mod 5 |
| PAINTER: BRUSH AND ROLLERResidentialPAIN0707-001 | $54.15 | $33.95 | $20.20 | OH20260006 Mod 1 |
How Allen County compares
The main painter rate in every county that has one, and how the pay splits here and nearby. All bars use the same scale.
Every county in Ohio
Wage and fringe benefits, nearby
- Allen Countybase $24.54$25.79
- Auglaize Countybase $17.91$28.76
- Putnam Countybase $17.91$28.76
- Hardin Countybase $17.91$28.76
Painter rates in nearby counties
Current DOL rates. Davis-Bacon rates are set for groups of counties, so neighbours often share them; the county where the work is done decides.
| County | Classification | Base + fringe | Base | vs Allen County |
|---|---|---|---|---|
| Auglaize County | PAINTER (BRUSH AND ROLLER) | $28.76 | $17.91 | +$2.97 |
| Putnam County | PAINTER (BRUSH AND ROLLER) | $28.76 | $17.91 | +$2.97 |
| Hardin County | PAINTER (BRUSH AND ROLLER) | $28.76 | $17.91 | +$2.97 |
| Van Wert County | PAINTER (BRUSH AND ROLLER) | $28.76 | $17.91 | +$2.97 |
| Hancock County | PAINTER (BRUSH AND ROLLER) | $28.76 | $17.91 | +$2.97 |
| Shelby County | PAINTER (BRUSH AND ROLLER) | $28.76 | $17.91 | +$2.97 |
| Allen County | PAINTER (BRUSH AND ROLLER) | $25.79 | $24.54 |
More from DOL on this rate
- DOL wage determination
- SAM.gov wage determinations
- Davis-Bacon determinations list journeyworker rates. Apprentices in a program registered with DOL or a recognized state agency can be paid the program's percentage of the rate, within its ratio; anyone else gets the full rate (29 CFR 5.5(a)(4)).
Are you being paid this rate?
Add your base pay to the fringe your employer pays for you, in cash or into plans, and compare the sum with the total. The Department of Labor's Wage and Hour Division takes complaints: 1-866-487-9243, or dol.gov/agencies/whd/contact/complaints.
Source
U.S. Department of Labor, Wage and Hour Division (DOL), wage determination OH20260068 Mod 1, published May 18, 2026: sam.gov/wage-determination/OH20260068/1
We read every active Ohio Davis-Bacon wage determination from SAM.gov's own data and check every number with a second, independent read of the same file. DOL prints no total; ours is base plus fringe. How we check · Download Allen County as CSV · Report an error