Skip to content

Home / Idaho / Franklin County / Operating Engineer

Franklin County, ID · Operating Engineer

Operating Engineer prevailing wage in Franklin County, Idaho

Which kind of construction is the job?

The kind of construction decides the rate: each wage determination covers one. Residential covers homes and apartments up to four stories.

$49.93an hour, base wage + fringe benefits (our sum) · CRANE

$31.81 base wage + $18.12 fringe benefits

OPERATOR: CRANE · UAVGID0002

$32.79an hour, base wage + fringe benefits (our sum)

$23.34 base wage + $9.45 fringe benefits

OPERATOR: CRANE · SUID2013-026

$57.48an hour, base wage + fringe benefits (our sum)

$36.98 base wage + $20.50 fringe benefits

POWER EQUIPMENT OPERATOR: CRANE · ENGI0302-006

On federally funded or assisted building construction in Franklin County, an operating engineer working as crane must be paid at least $49.93 an hour: a $31.81 base wage plus $18.12 in fringe benefits, under wage determination ID20260105 (modification 3). DOL prints no total, so $49.93 is our sum of the two.

Wage determination ID20260105, modification 3, published May 18, 2026, for building construction; rate identifier UAVGID0002 (January 3, 2025). Checked against sam.gov on October 25, 2026.

On federally funded or assisted highway construction in Franklin County, an operating engineer must be paid at least $32.79 an hour: a $23.34 base wage plus $9.45 in fringe benefits, under wage determination ID20260098 (modification 1). DOL prints no total, so $32.79 is our sum of the two.

Wage determination ID20260098, modification 1, published May 18, 2026, for highway construction; rate identifier SUID2013-026 (June 17, 2013). Checked against sam.gov on October 25, 2026.

On federally funded or assisted heavy construction in Franklin County, an operating engineer must be paid at least $57.48 an hour: a $36.98 base wage plus $20.50 in fringe benefits, under wage determination ID20260109 (modification 2). DOL prints no total, so $57.48 is our sum of the two.

Wage determination ID20260109, modification 2, published May 18, 2026, for heavy construction; rate identifier ENGI0302-006 (January 1, 2025). Checked against sam.gov on October 25, 2026.

Davis-Bacon is the only prevailing wage here (federally funded or assisted work). Idaho repealed its law in 1985 (DOL state table).

DOL lists 15 operating engineer rates for Franklin County, from $27.98 to $57.48 an hour. See all of them.

Base wage and fringe benefits: $31.81 + $18.12

The base wage is the taxable hourly wage. DOL prints the fringe benefits as one hourly figure, not itemized; it can go to health, pension, vacation and training plans, or be paid as cash where the state allows.

Base wage (taxable)$31.81
Fringe benefits (one figure, not itemized)$18.12
Base + fringe benefits (our sum; DOL prints no total)$49.93

Base wage and fringe benefits: $23.34 + $9.45

The base wage is the taxable hourly wage. DOL prints the fringe benefits as one hourly figure, not itemized; it can go to health, pension, vacation and training plans, or be paid as cash where the state allows.

Base wage (taxable)$23.34
Fringe benefits (one figure, not itemized)$9.45
Base + fringe benefits (our sum; DOL prints no total)$32.79

Base wage and fringe benefits: $36.98 + $20.50

The base wage is the taxable hourly wage. DOL prints the fringe benefits as one hourly figure, not itemized; it can go to health, pension, vacation and training plans, or be paid as cash where the state allows.

Base wage (taxable)$36.98
Fringe benefits (one figure, not itemized)$20.50
Base + fringe benefits (our sum; DOL prints no total)$57.48

When does this rate change?

Every operating engineer rate in Franklin County

As DOL lists them. The highlighted row is the one this page leads with.

  1. POWER EQUIPMENT OPERATOR: CRANEHeavy · ENGI0302-006$57.48
  2. POWER EQUIPMENT OPERATOR: LOADERBuilding · ENGI0302-012$52.24
  3. POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOEHeavy · ENGI0302-011$52.24
  4. POWER EQUIPMENT OPERATOR: FORKLIFTBuilding · ENGI0302-012$51.73
  5. OPERATOR: CRANEBuilding · UAVGID0002$49.93
  6. OPERATOR: BACKHOE/EXCAVATOR/TRACKHOEBuilding · SUID2021-006$39.31
  7. OPERATOR: CRANEHighway · SUID2013-026$32.79
  8. OPERATOR: ROLLERHighway · SUID2013-026$32.40
  9. OPERATOR: FORKLIFTHighway · SUID2013-026$32.30
  10. OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE)Highway · SUID2013-026$31.36
  11. OPERATOR: BROOM/SWEEPERHighway · SUID2013-026$30.27
  12. OPERATOR: SCREEDHighway · SUID2013-026$29.52
  13. OPERATOR: BOBCAT/SKID STEER/SKID LOADERHighway · SUID2013-026$29.35
  14. OPERATOR: OILERHighway · SUID2013-026$28.77
  15. OPERATOR: ROLLER (SUBGRADE)Highway · SUID2013-026$27.98
Hourly rate of each operating engineer classification in Franklin County, highest first, split into wage and fringe benefits.
ClassificationBase wageFringe benefitsTotal rateWD
POWER EQUIPMENT OPERATOR: LOADERBuildingENGI0302-012$36.14 $16.10 $52.24 ID20260105 Mod 3
POWER EQUIPMENT OPERATOR: FORKLIFTBuildingENGI0302-012$36.33 $15.40 $51.73 ID20260105 Mod 3
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOEBuildingSUID2021-006$28.92 $10.39 $39.31 ID20260105 Mod 3
OPERATOR: CRANEBuildingUAVGID0002$31.81 $18.12 $49.93 ID20260105 Mod 3
POWER EQUIPMENT OPERATOR:(GROUP 6): BLADE OPERATOR, BACKHOE/TRACKHOE/EXCAVATOR (3/4 YDS- 3 1/2 YDS, FRONT END LOADER (OVER 4 YDS TO AND INCLUDING 7YDS) ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE. BOOM PAY: ALL CRANES AND CONCRETE PUMP BOOM TRUCKS 100 FT TO 150 FT $.15 OVER SCALE 150 FT TO 200 FT $.30 OVER SCALE OVER 200 FT $.45 OVER SCALEHighwayENGI0370-044
POWER EQUIPMENT OPERATOR:(GROUP 6): BLADE OPERATOR, BACKHOE/TRACKHOE/EXCAVATOR (3/4 YDS- 3 1/2 YDS, FRONT END LOADER (OVER 4 YDS TO AND INCLUDING 7YDS) ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE. BOOM PAY: ALL CRANES AND CONCRETE PUMP BOOM TRUCKS 100 FT TO 150 FT $.15 OVER SCALE 150 FT TO 200 FT $.30 OVER SCALE OVER 200 FT $.45 OVER SCALE
DOL prints this rate per day: $36.98 base, fringe “16.10”.
———ID20260098 Mod 1
POWER EQUIPMENT OPERATOR: GROUP 8 BULLDOZER ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVEHighwayENGI0370-044
POWER EQUIPMENT OPERATOR: GROUP 8 BULLDOZER ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE
DOL prints this rate per day: $37.58 base, fringe “16.10”.
———ID20260098 Mod 1
POWER EQUIPMENT OPERATOR: GROUP 7 GRADER (FINE), FRONT END LOADER (OVER 7 YDS), HEAVY DUTY MECHANIC ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE. BOOM PAY: ALL CRANES AND CONCRETE PUMP BOOM TRUCKS 100 FT TO 150 FT $.15 OVER SCALE 150 FT TO 200 FT $.30 OVER SCALE OVER 200 FT $.45 OVER SCALEHighwayENGI0370-044
POWER EQUIPMENT OPERATOR: GROUP 7 GRADER (FINE), FRONT END LOADER (OVER 7 YDS), HEAVY DUTY MECHANIC ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE. BOOM PAY: ALL CRANES AND CONCRETE PUMP BOOM TRUCKS 100 FT TO 150 FT $.15 OVER SCALE 150 FT TO 200 FT $.30 OVER SCALE OVER 200 FT $.45 OVER SCALE
DOL prints this rate per day: $37.35 base, fringe “16.10”.
———ID20260098 Mod 1
POWER EQUIPMENT OPERATOR: GROUP 5 ELEVATING GRADER OPERATOR, BACKHOE/TRACKHOE/EXCAVATOR (UNDER 3/4 YDS) ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE. BOOM PAY: ALL CRANES AND CONCRETE PUMP BOOM TRUCKS 100 FT TO 150 FT $.15 OVER SCALE 150 FT TO 200 FT $.30 OVER SCALE OVER 200 FT $.45 OVER SCALEHighwayENGI0370-044
POWER EQUIPMENT OPERATOR: GROUP 5 ELEVATING GRADER OPERATOR, BACKHOE/TRACKHOE/EXCAVATOR (UNDER 3/4 YDS) ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE. BOOM PAY: ALL CRANES AND CONCRETE PUMP BOOM TRUCKS 100 FT TO 150 FT $.15 OVER SCALE 150 FT TO 200 FT $.30 OVER SCALE OVER 200 FT $.45 OVER SCALE
DOL prints this rate per day: $36.81 base, fringe “16.10”.
———ID20260098 Mod 1
POWER EQUIPMENT OPERATOR: GROUP 4 FRONT END LOADER (UP TO 4YD) ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVEHighwayENGI0370-044
POWER EQUIPMENT OPERATOR: GROUP 4 FRONT END LOADER (UP TO 4YD) ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE
DOL prints this rate per day: $36.64 base, fringe “16.10”.
———ID20260098 Mod 1
OPERATOR: SCREEDHighwaySUID2013-026$22.30 $7.22 $29.52 ID20260098 Mod 1
OPERATOR: ROLLER (SUBGRADE)HighwaySUID2013-026$19.99 $7.99 $27.98 ID20260098 Mod 1
OPERATOR: ROLLERHighwaySUID2013-026$24.26 $8.14 $32.40 ID20260098 Mod 1
OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE)HighwaySUID2013-026$24.24 $7.12 $31.36 ID20260098 Mod 1
OPERATOR: OILERHighwaySUID2013-026$22.25 $6.52 $28.77 ID20260098 Mod 1
OPERATOR: FORKLIFTHighwaySUID2013-026$23.13 $9.17 $32.30 ID20260098 Mod 1
OPERATOR: CRANEHighwaySUID2013-026$23.34 $9.45 $32.79 ID20260098 Mod 1
OPERATOR: BROOM/SWEEPERHighwaySUID2013-026$22.80 $7.47 $30.27 ID20260098 Mod 1
OPERATOR: BOBCAT/SKID STEER/SKID LOADERHighwaySUID2013-026$21.15 $8.20 $29.35 ID20260098 Mod 1
POWER EQUIPMENT OPERATOR: CRANEHeavyENGI0302-006$36.98 $20.50 $57.48 ID20260109 Mod 2
POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOEHeavyENGI0302-011$36.14 $16.10 $52.24 ID20260109 Mod 2

How Franklin County compares

The main operating engineer rate in every county that has one, and how the pay splits here and nearby. All bars use the same scale.

Every county in Idaho

$22.23Power$49.93Bannock
FranklinNearby: Bear Lake $36.22, Oneida $36.22, Bannock $49.93Each column is a group of counties with about the same main rate; its height is how many. 0 counties pay more than Franklin, 1 the same, 42 less.

Wage and fringe benefits, nearby

  1. Franklin Countybase $31.81$49.93
  2. Bear Lake Countybase $26.22$36.22
  3. Oneida Countybase $26.22$36.22
  4. Bannock Countybase $31.81$49.93

Operating Engineer rates in nearby counties

Current DOL rates. Davis-Bacon rates are set for groups of counties, so neighbours often share them; the county where the work is done decides.

CountyClassificationBase wageTotal ratevs Franklin County
Franklin CountyOPERATOR: CRANE$31.81 $49.93 
Bannock CountyOPERATOR: CRANE$31.81 $49.93 same
Bear Lake CountyOPERATOR: CRANE$26.22 $36.22 −$13.71
Oneida CountyOPERATOR: CRANE$26.22 $36.22 −$13.71
Caribou CountyOPERATOR: CRANE$26.22 $36.22 −$13.71
Bingham CountyOPERATOR: CRANE$26.22 $36.22 −$13.71
Power CountyOPERATOR: BACKHOE/EXCAVATOR$22.23 $22.23 −$27.70

Idaho operating engineer prevailing wage by county, with a map

More from DOL on this rate

All Franklin County prevailing wage rates

Are you being paid this rate?

Add your base pay to the fringe your employer pays for you, in cash or into plans, and compare the sum with the total. The Department of Labor's Wage and Hour Division takes complaints: 1-866-487-9243, or dol.gov/agencies/whd/contact/complaints.

Source

U.S. Department of Labor, Wage and Hour Division (DOL), wage determination ID20260105 Mod 3, published May 18, 2026: sam.gov/wage-determination/ID20260105/3

We read every active Idaho Davis-Bacon wage determination from SAM.gov's own data and check every number with a second, independent read of the same file. DOL prints no total; ours is base plus fringe. How we check · Download Franklin County as CSV · Report an error